Coal Reserves

The table below details the total Coal Reserves estimated as at 31 December 2023.

Table 10: Coal Reserves

    2023 2022
      RoM and saleable tonnes4 RoM and saleable tonnes4 %  
change  
in  
RoM5
Operation1 LoM  
(years)3
Category RoM
(Mt)
RoM
moisture
%
Export
(Mt)
Thermal
(Mt)
Metal-
lurgical
(Mt)
RoM
(Mt)
RoM
moisture
%
Export
(Mt)
Thermal
(Mt)
Metal-
lurgical
(Mt)
Matla6
(UG)
Proved 126 9.5 126 130 9.5 130 (3)
(captive market) 1+ Probable 31 9.5 29 38 9.5 38 (18)
100% attributed to Exxaro2   Total 157 9.5
162
167.4 9.5   167
(6)
    Inferred Resourcesinside LoMP 5   6 (11)
Leeuwpan7
(OC)
Proved 30.5 3.1 22.7 36.1 3.1 26.4 (15)
(commercial market) 6 Probable 3.3 2.6 1.5 3.3 2.6 1.5 – 
100% attributed to Exxaro2   Total 33.8 3.0   22.7 1.5 39.4 3.1   26.4 1.5 (14)
Mafube8   Inferred Resourcesinside LoMP 0.0 0.0
(OC) Proved 82.6 8.0 46.9 9.7 80.6 8.0 44.2 12.7
(commercial market) 20 Probable 32.0 8.0 20.6 0.6 40.8 8.0 25.6 1.2 (22)
50% attributed to Exxaro2   Total 114.7 8.0 67.5 10.3
121.4 8.0 69.8 13.9
(6)
    Inferred Resourcesinside LoMP 0.2
  1.6 (87)
Belfast
(OC)
Proved 33.2 3.4 29.4 35.8 3.4 31.6 (7)
(commercial market) 10 Probable 1.4 2.9 1.1 1.4 2.9 1.1 – 
100% attributed to Exxaro2   Total 34.6 3.4 30.5
37.2 3.4 32.7

(7)
    Inferred Resourcesinside LoMP 1.0 1.0
Grootegeluk mine
(OC)
  Proved 1 971 3.0 123 742 56 2 034 3.0 126 776 58 (3)
(commercial market) 18+ Probable 550 3.0 37 191 6 550 3.0 37 191 6 – 
100% attributed to Exxaro2 Total 2 521 3.0 160 933 62 2 584 3.0 163 967 64 (2)
    Inferred Resourcesinside LoMP 73  


73
  (1)
Thabametsi project
(OC)
Proved
(IPP market) 23 Probable 130 3.0 127 130 3.0 127 – 
100% attributed to Exxaro2   Total 130 3.0
127
130 3.0
127
– 
    Inferred Resourcesinside LoMP 0.0 0.0
  • Rounding of figures may cause computational discrepancies.
  • Tonnages are quoted in metric tonnes and million tonnes is abbreviated as Mt.
  • Inferred Resources inside LoMP refer to Inferred Resources considered for the LoMP. These Resources have not been converted to Reserves.
  • Coal Reserves are quoted on a RoM Reserve tonnage basis, which represents tonnages delivered to the plant at an applicable moisture and quality basis.
  • Saleable Reserve tonnage represents the product tonnes of coal available for sale on an applicable moisture basis.
  • All changes more than 10% in the total Reserves of an operation are explained.
  • Resource to Reserve modifying factors per operation are stated in the ancillary section.
1 Operation refers to operating mine or significant project. Mining method: opencast (OC) or underground (UG).
2 Figures are reported at 100%, irrespective of percentage attributable to Exxaro, and refer to 2023 only.
3 The + symbol is used in instances where the scheduled LoMP extends beyond the expiry of the mining right. In each instance, Exxaro reasonably expects the mining right to be renewed.
4 Export refers to export thermal coal except at Grootegeluk mine, where it refers to semi-soft coking coal suitable for the export and inland markets.
5 The percentage difference between 2023 reported RoM and 2022 reported RoM. Brackets signify a decrease.
6 The mining right lapses in 2025, the LoM is scheduled for an additional 13 years thereafter. The change in the Probable Reserve is due to the update of the LoMP and reconciliation.
7 The decrease is the result of new drill hole information received as well as layout losses that occurred during the execution of the mine plan.
8 Changes are the result of the movement in the Resource base and exclusion of area due to environmental considerations.

Service bay for production trucks

Table 11: Coal Reserve qualities

    THERMAL saleable
(Proved and Probable)
METALLURGICAL saleable
(Proved and Probable)
COKING saleable
(Proved and Probable)
    Tonnes CV % % % Yield Tonnes CV % % % Yield Tonnes CV   %   %   % Yield
Operation Seam/layer (Mt)1 MJ/kg VM Ash S % (Mt)1 MJ/kg VM Ash % (Mt)1 MJ/kg   VM Ash S %
Matla mine Seam 2 57.0 22.00 23.80 22.00 0.90     100                        
Seam 4 99.7 18.80  22.20 29.50 1.00    100                        
Leeuwpan mine TC2 8.4 21.35 18.00 30.36 1.14      64                        
BC2 14.3 23.60 23.60 22.55 0.91      69 1.5 28.46 8.10 13.68 0.95 44            
Mafube mine Middlings 29.0 21.46 21.59 26.58 0.57      28                        
  Export 38.5 26.51 26.75 13.46 0.46      37                        
  Crush and 10.3 19.58 20.54 29.25 0.97     100                        
  stack                        
Belfast mine RB2 18.4 26.57 24.41 13.99 0.44 66              
  RB3 6.7 24.25 22.20  21.00 0.97    100              
  >4 800kcal/kg 3.7 23.74 24.00  21.59   0.65    13              
  Filter cake 1.7 20.82 19.83 27.73 1.16      6              
Grootegeluk mine All seams 933 21.60 25.10    33.20 1.30    40 62 28.70 23.90 14.00 0.60 60 160 28.6   34.80 13.10 1.14     12
Thabametsi T1 64 12.70 20.00 53.90 1.10      98              
project3
T2 63 11.30 19.00 55.70 1.00      98
  • Rounding of figures may cause computational discrepancies.
  • Volatile matter (VM), sulphur (S), ash content (ash) and gross calorific value (CV).
  • Saleable Coal Reserve tonnage represents the product tonnes of coal available for sale on an applicable moisture and air-dried quality basis.
1 Saleable product tonnages are quoted in metric tonnes and million tonnes is abbreviated as Mt.
2 Top coal (TC) and bottom coal (BC).
3 Based on Thabametsi bench configuration as defined in phase 1 of the feasibility study.